1900 W Lawrence Completed
1900 W. Lawrence, a former Sears department store, has been completed. The nearly 100-year-old building now features retail space and apartments.
Read more at REJournals
General Contracting | Construction Management | Design + Build
1900 W. Lawrence, a former Sears department store, has been completed. The nearly 100-year-old building now features retail space and apartments.
Read more at REJournals
The restaurant marks the first Florida location for the Chicago-based chain.
Read more at Business Observer
Summit Design + Build, LLC, recently completed the renovation of a 4-story mixed-use commercial building located at 444 N. Orleans in Chicago’s River North neighborhood. The project, which started in early 2019, included the new construction of a vertical addition to bring the building to a total of five stories.
The existing, 21,000 square foot building that stands at the southwest corner of Illinois and Orleans Street in River North was formerly home to a variety of corporate office tenants and high-end furniture stores prior to being vacated to make way for the renovations. The building now totals over 25,000 square feet, offering first-floor retail space and office or showroom space on the remaining floors in the in-demand River North submarket, just blocks away from the Merchandise Mart, the East Bank Club and multiple public transit lines.
In addition to completing the vertical addition, construction included a major interior renovation with all new MEP systems, new bathrooms, new windows throughout allowing for maximum natural light, 78 feet of first floor retail frontage, and a new, relocated elevator for a more efficient floor plan.
The building’s exterior was also updated by utilizing the existing coarse stucco façade as a scratch coat to install a new, smooth stucco finish. Selective areas of the existing brick façade were removed and replaced by a Dekton ventilated porcelain façade.
444 N. Orleans is being redeveloped by The Lelyn Group. von Weise Associates is providing architectural services.
Summit Design + Build’s new headquarters at 1040 W. Fulton has been awarded the 2021 U.S. Wood Design Award for Regional Excellence. Awarded by WoodWorks – Wood Products Council, the award celebrates excellence in wood building design and recognizes building designers for their skill and ingenuity.
Read more at PR Newswire
The Southeast office of general contractor Summit Design + Build, recently completed the interior fit-out of Billy Bricks Wood Fired Pizza in Clearwater, FL. The family owned and operated pizzerias have been serving Chicagoland since 2005 and the new Clearwater location marks its 10th restaurant. The restaurant is known for its thin-crust, Neapolitan Inspired pizzas baked in an authentic wood-fired oven.
The project, located at 1100 Cleveland Street, included the 2,506 square foot fit-out of an existing shell tenant space in an existing apartment building (1100 Apex). The build-out of the pizza restaurant included a kitchen with wood-fired pizza oven, dining area, bar area and restrooms.
Kimmich Smith Architecture, LLC served as the project architect.
President of Summit Design + Build, Adam Miller, discusses the impact 2020 has had on the construction industry and what 2021 holds for Summit Design + Build.
Read more at REBusiness Online
Summit Design + Build’s Senior Project Manager, Kevin Criner, shares his insights on how to complete a construction project under budget without sacrificing quality and project schedule.
There are three aspects that are commonly thrown around while determining the success of a construction project: quality, timeliness and within budget. Often one is sacrificed to achieve the other but, in my eyes, (and most clients’ eyes) all three are essential. With numerous years of construction project management experience under my belt, I want to share my take on how to successfully complete a project within or under budget, while keeping quality and schedule in mind. Be aware that a project within budget is the project itself and not the bottom line profit you turn into your boss at the end of the job. An owner with a blown budget can be just as detrimental.
The “Not Included” Winter Conditions
Obtain proper subcontractor coverage and understand scope– You should always be mindful of what you are plugging into a bid estimate. During the hustle and bustle of putting a bid together this might be tough, but if you have three prices for a particular trade you should ultimately be able to understand what they have or what they may have missed. Remember, you must buy the scope from each subcontractor. Don’t plug in low numbers just to drive the number down on a piece of paper, that number isn’t real.
Confirm the client understands what you have– It is very common when getting scoped for a job to become a “yes man/women.” After all, you want the project and you’ve put in a lot of work to get to the table. It is important to remember that because you are at the table to begin with, your number is something they can live with. If it is substantial and you do not have it, let it be known. The cost of it will not go away. The same concept applies when negotiating a contract. Multiple meetings will be held over weeks/months/years in which many subjects are covered. If the owner insists on leaving something out of the budget, make sure you are very clear that it is being left out each step of the way. In some cases, if you know it is going to be a cost, fight to have it included. The project will run smoother should you not have to get a change order for it later.
Negotiate Wisely– If you must skim a little to win the job or to make the job happen, you should always know where that money is coming from. Lower your budget in areas where you can make the numbers work.
Avoid the Big One– “The Big One” (a large change order) will more than likely come from a failure to achieve one of the items above. Sometimes a client voluntarily makes a big add to the scope of the job or a change derives from a source you have no control over (i.e., municipality, utility company). It is extremely important to go over these things during preconstruction and try to get them in the budget. You know it’s a possibility, so why not discuss it?
Buy out the details– It is your job to buy the plans from the subcontractor. Make sure every item in each plan detail has a subcontractor attached to it. Run through the schedule and make sure each sequence makes sense. Make sure you aren’t buying an ideal schedule from one subcontractor that cannot work. This results in changes and/or delays to the schedule.
Challenge each change order– When there is inevitably going to be a change in something understand the work involved. Do not be the pass-through between the subcontractor and the client. Agree with what you are presenting and have multiple solutions to present. Very commonly there is an easier way to achieve the same thing. Get creative and come up with solutions that are least detrimental to the budget, schedule and quality of construction.
Preserve the schedule (time is money)– Subcontractor schedule input should be provided as early on as possible. Your perfect schedule usually has some duration or sequence errors and the subcontractors can help you fix it. Also, in some instances, they can help you pick up time. Sub durations should also be constantly monitored. Just because it doesn’t seem like a delay at the time, it could be in the very near future. If the schedule is not maintained, it will result in an accelerated/overtime schedule that ultimately costs the project money.
The Utility Company Add
Timely Buy-Out– Knowing what savings you do or do not have determines your strategy throughout the project. If you have un-bought scope then you are at risk of additional overages you are not projecting for. In budget management this can be detrimental to the bottom line.
Monitor the budget– If you know where your numbers are then you know when you do or do not have money to spend to handle an issue and push the project through. If you wait for monthly (or worse) reconciliations then you may be approving too much or spending time fighting something you could have handled prior.
The Missed Blocking Scope
It is also important to remember that the budget should be properly developed, maintained, and protected throughout the duration of a project. There should be no surprise come the end of the job. Keeping all the above points in mind, an under budget, on-time, quality construction project should be well within reach. Do you have an upcoming construction project? Reach out to our team of construction experts to get started!
Chief, a private women’s network, opens first Chicago clubhouse
Summit Design + Build, has completed the build-out of a 14,000 square foot clubhouse for Chief. Chief, launched in 2019, is a private network for women who are C-level executives or rising VP’s. The company was founded to help drive women into positions of power and keep them there.
The clubhouse is located on the second and third floors of 1040 W. Fulton, a newly constructed, heavy timber building that is also home to Summit Design + Build’s new headquarters. The fit-out of the space features multiple conference rooms, a speaking area, a bar and lounge area, as well as a roof top deck and green roof space. The clubhouse will be used to help women make connections through peer groups, workshops, sponsored events and dinners. The clubhouse is the first Chicago location for Chief, which also has clubhouses in New York and Los Angeles.
Chicago-based GREC Architects served as the project architect.
Summit Design + Build’s Project Engineer II, Ben Cohen, shares his insights on how to master an adaptive reuse construction project.
Adaptive reuse is the process of revitalizing old buildings for new and modern functions, other than those the building was originally designed. These projects play an extremely important role in maintaining the aesthetic of historic districts and protecting architecturally significant buildings. In order to master adaptive reuse, you must always expect the unexpected and take the following key points into consideration.
In order to accomplish the modern open floor plan design that is typical for today’s new structures, selective demolition and exploratory work are necessary to better understand the true existing structure of the building. It is extremely common to find undocumented adaptions to the “existing” drawings that impact layout, design, or have structural implications. In order to help flush these potential show-stopper issues out ahead of time, it is extremely important to have surveys and exploratory demolition done to confirm dimensions and assumptions before the general contractor is fully mobilized and beginning work on site. It’s not uncommon to come across conditions such as undocumented underground storage tanks, abandoned basements, structural wall footings that were narrower than the wall that was bearing on it, walls installed at all sorts of angles off of plumbing, and roofs built over other roofs! The more investigatory work you can do to give your general contractor a fuller picture the better.
When working in old buildings, hazardous construction materials such as asbestos, lead, mold and refrigerant are common to encounter. Dealing with, or at the very least surveying and identifying these materials before construction commences on site is extremely important, as discovering any of these during the selective demolition process could trigger work to stop until the materials are properly abated.
According to Architect Magazine’s article: When it Leaks it Pours, water intrusion makes up more than 70 percent of construction litigation. In order to avoid a lot of headaches down the road make sure to have a 3rd party expert review the architectural drawings and/or the site conditions to make sure the designs proposed apply to, and will work well with, the existing structure. The specialists we’ve had the most success with in the past have been Wiss, Janney, Elstner Associates, Inc. Having a separate pair of eyes on the drawings to ensure the building envelope design is robust and detailed to be fully water tight is money well spent.
Depending on the age of the building, and of the mechanical, electrical and plumbing elements therein, you may choose to re-use, abandon in place, or fully remove and re-do these components. If the plan is to keep these elements in a workable condition, make sure the existing equipment meets the current code. If so, a plan must be made to protect them from water, dust and damage during the construction process. If the plan is to demolish and start fresh, make sure that all assumptions and dimensions are verified on-site. Are the existing shafts sufficiently sized for the new ductwork, plumbing risers and electrical homeruns? Do the duct sizes and light placements work with the given floor to ceiling heights? Is there sufficient water pressure for any additions being made to the existing structure? The more of these types of questions you can answer before work starts on site the better off you’ll be.
In conclusion, the way to master adaptive re-use projects is to do your due diligence. Surveying and exploratory work are upfront costs that are well worth the expense and will help reduce headaches and costly change orders while the full gears of construction are in motion. Additionally, make sure to work with general contractors who have done this type of work before. When it comes to working in older buildings, experience plays a major role. Check out your GC’s previous projects, ask for references and walk the space with them to see how comfortable they feel with your vision. You can check out Summit Design + Build’s extensive adaptive reuse work here. Adaptive reuse is an incredible way to breathe new life into an old building while preserving the historic value and local resources and will be an undertaking worth pursuing if you follow these guidelines!